Why the Mir Alam Tank Bridge Is a Game-Changer for South Hyderabad’s Road Network
The Mir Alam Tank Bridge Hyderabad Project 2025 marks a major milestone in Telangana’s infrastructure roadmap. Sanctioned at a cost of ₹430 crore, this 2.8-kilometer, four-lane bridge aims to drastically improve road connectivity between the Bengaluru National Highway (NH-44) and key residential and commercial areas such as Chintalmet, Rajendranagar, and Bahadurpura.
Designed to relieve chronic congestion and create a direct route over the historically significant Mir Alam Tank, the project is expected to reshape traffic movement across South Hyderabad and support long-term urban development.

Key Facts – Mir Alam Tank Bridge Hyderabad Project (2025):
- Location: Mir Alam Tank, South Hyderabad
- Length: 2.8 kilometers
- Cost: ₹430 crore
- Execution Mode: EPC (Engineering, Procurement, and Construction)
- Purpose: Reduce traffic and improve connectivity between NH-44 and Chintalmet Road
How the Mir Alam Tank Bridge Will Improve Traffic Flow in Hyderabad
For decades, commuters traveling between Rajendranagar, Bahadurpura, and the Bengaluru Highway have dealt with severe bottlenecks and time-consuming detours around the historic Mir Alam Tank. The bridge is strategically designed to directly connect Shastripuram (NH-44) to Chintalmet Road, offering a smoother, shorter alternative route that bypasses congestion hotspots.
Once completed, the bridge is expected to:
- Drastically reduce travel time in the southern corridor
- Relieve pressure on internal roads near the Hyderabad Zoo and old city areas
- Serve as a vital link between the growth-intensive suburbs and major arterial highways
Mir Alam Tank Bridge Project Details – EPC Design, Route & Connectivity
Total Length & Width
- Length: 2.8 km
- Design: Four-lane structure with provisions for drainage, lighting, and future traffic scalability
Project Execution Model
- Delivered under the Engineering, Procurement, and Construction (EPC) mode
- Led by the Musi Riverfront Development Corporation Ltd. (MRDCL)
- Structured to include independent quality audits and third-party supervision for transparency

Timeline
- Tendering Process: To begin within one month
- Construction Duration: 24 months from the date of site handover
- Simultaneous Land Acquisition: Streamlined acquisition plan to avoid project delays
Quality Checks & Engineering Oversight in Telangana’s ₹430 Crore Bridge Plan
To ensure structural soundness and design integrity, the bridge’s detailed drawings and engineering plans will undergo a thorough review by leading technical institutes, such as:
- IIT Hyderabad
- NIT Warangal
- JNTU Hyderabad
This added layer of oversight guarantees that the bridge will adhere to national safety standards and incorporate sustainable engineering practices for long-term resilience.
Additionally, a dedicated Project Management Consultancy (PMC) will monitor daily progress, material quality, and safety benchmarks—right from the foundation phase to final touches.

Revised Budget and Bridge Length: What Changed in 2025 Plan
Compared to the earlier ₹363 crore proposal, the updated ₹430 crore plan includes:
Feature | Earlier Plan | Revised Plan (2025) |
Total Cost | ₹363 crore | ₹430 crore |
Bridge Length | ~2.65 km | 2.8 km |
Scope of Design | Basic four-lane | Modern, wider lanes + utilities |
Execution Mode | Conventional EPC | Modernized EPC with enhanced PMC & vetting |
Supervision & Quality Control | Internal checks | Independent PMC + IIT/NIT vetting |
The revision ensures better structural strength, upgraded aesthetics, and compatibility with future smart city projects.
Urban Mobility Benefits of the Mir Alam Tank Bridge in Hyderabad
The Mir Alam Tank Bridge is more than concrete and steel—it represents a vision of connected urbanization. Here’s how it will benefit the city:
Direct Advantages:
- Smoother travel between Hyderabad’s core and southern suburbs
- Improved logistics for commercial transport and daily commuters
- New access paths for emergency services and public transport
Indirect Gains:
- Reduced vehicular emissions in nearby eco-sensitive zones like the Hyderabad Zoo
- Lower fuel consumption and improved air quality in South Hyderabad
- Support for tourism and eco-tourism activities around the Mir Alam Tank lakefront
Project Timeline & Next Steps for the Mir Alam Tank Bridge
With tenders expected to roll out within a month, and all necessary funds sanctioned, the stage is set for execution. MRDCL and associated bodies are now finalizing contracts, selecting contractors, and initiating land clearance where necessary.
The next two years will be crucial as Hyderabad watches one of its most important infrastructure upgrades take shape—block by block, span by span.
Conclusion: A Transformational Step for Hyderabad’s Transport Infrastructure
The ₹430 crore Mir Alam Tank Bridge is not just a civil engineering project; it’s a vital investment in Hyderabad’s future. With thoughtful design, modern construction methods, and strict quality oversight, this bridge is poised to become a signature piece of infrastructure that reflects the city’s growth and ambition.
As Telangana continues to scale up urban mobility and infrastructure across its districts, the Mir Alam Tank Bridge stands as a symbol of well-planned progress—rooted in technical excellence, public necessity, and long-term vision.
FAQ
1. What is the total cost and route of the Mir Alam Tank Bridge in Hyderabad?
The Mir Alam Tank Bridge is being built at a cost of ₹430 crore under the EPC (Engineering, Procurement, and Construction) model. The total length of the bridge is 2.8 kilometers, stretching from Shastripuram (NH-44) to Chintalmet Road, passing over the historic Mir Alam Tank. This route was strategically selected to ease traffic congestion and provide a more direct connection between Rajendranagar, Bahadurpura, and Bengaluru Highway (NH-44).
2. When will the Mir Alam Tank Bridge be completed and open for public use?
As per the latest updates in 2025, the tendering process for the project is scheduled to begin within a month. Once construction starts, the bridge is expected to be completed within 24 months. This means the bridge could likely open for public use by late 2027, provided there are no delays in land acquisition or approvals.
3. How will the Mir Alam Tank Bridge help reduce traffic in South Hyderabad?
Currently, commuters face long detours and bottlenecks around the Mir Alam Tank, especially when traveling between NH-44, Rajendranagar, and Bahadurpura. The new bridge will provide a straight, uninterrupted route, cutting down travel time significantly and decongesting roads near the Hyderabad Zoo, Bahadurpura Junction, and Old City areas. It will also act as a pressure valve by diverting commercial and local traffic from densely packed residential areas.
4. Which areas will benefit most from the Mir Alam Tank Bridge project?
The bridge is expected to directly benefit several high-density and fast-growing neighborhoods in South Hyderabad, including:
Rajendranagar
Chintalmet
Bahadurpura
Shastripuram
Attapur
These areas currently suffer from limited east-west connectivity. The bridge will offer a major link between these zones and key city corridors like NH-44, reducing reliance on interior roads and improving commute times for thousands of residents daily.
5. Who is constructing the ₹430 crore Mir Alam Tank Bridge and what is the EPC model?
The project is being executed by the Musi Riverfront Development Corporation Ltd. (MRDCL) under the EPC model, which stands for Engineering, Procurement, and Construction. This means a single contractor will handle the entire process — from design and procurement of materials to final construction. The project will also include oversight from top engineering institutions like IIT Hyderabad and NIT Warangal to ensure quality and long-term structural stability.