Types of Earth Retention Systems and How to Choose One

Soldier piles, sheet piles, secant piles, soil nails and slurry walls compared, with soil and groundwater limits, OSHA triggers, reported costs and a free selector.

Dig a basement next to a street or an existing building and the soil around the hole wants to move in. An earth retention system is whatever holds it back while the work happens, and sometimes for the life of the structure. The choice shapes the budget, the schedule and the risk to the neighbors. This guide explains the main types, what ground each one suits, what the OSHA rules require, and how to narrow the options. The selector below gives a first shortlist for your own site.

Types of earth retention systems: quick answer
The main earth retention systems are soldier pile and lagging, steel sheet piles, secant and tangent pile walls, soil nail walls and slurry or diaphragm walls. Tiebacks and internal bracing are added to many of them for extra support. Groundwater decides most of the choice: sheet piles, secant piles and slurry walls can hold water back, while soldier piles and soil nails generally cannot.
SystemBest suited toMain limit
Soldier pile and laggingFast, low-cost temporary cuts above the water tableNot for high groundwater without dewatering
Steel sheet pileExcavation below groundwater, cofferdamsHard driving through boulders
Secant pileWater cutoff beside structures, obstructed groundExpensive, needs a skilled contractor
Tangent pileRobust wall where tiebacks cannot be usedNot watertight
Soil nail wallTop-down cuts in ground that stands brieflyPoor in loose, wet or soft soils
Slurry or diaphragm wallStiff wall for demanding deep workUsually the costliest option

When you legally need a protective system

On US work sites the starting point is OSHA Subpart P. Three thresholds matter:

  • 5 feet. Under 1926.652(a)(1), workers must be protected from cave-ins unless the excavation is entirely in stable rock, or is less than 5 ft deep and a competent person finds no sign of a potential cave-in.
  • 20 feet. Sloping or benching for excavations deeper than 20 ft must be designed by a registered professional engineer.
  • Any custom support system. Under 1926.652(c)(4), a support system that does not use OSHA’s appendices or manufacturer or tabulated data must be approved by a registered professional engineer, with a written design plan.

Sloping back is often the cheapest protection when you have the room. Earth retention becomes necessary when you do not: a property line, a road, a utility or a neighboring foundation is too close. If you are outside the US, your local rules apply. Our guide to shoring under IS codes covers Indian practice.

Building Estimate & BOQ Excel Kit cover
📚 Recommended Download
Building Estimate & BOQ Excel Kit
Type your building dimensions — get quantities, materials, a priced BOQ and cost per sq ft. 6 linked sheets, IS 1200-style measurement, editable rates.
✔ Editable Excel  ·  ✔ Instant download  ·  ✔ Lifetime access
Six section diagrams showing soldier pile and lagging, steel sheet pile, secant or tangent pile, soil nail wall, tieback anchors and internal bracing
The six common arrangements in section. Diagram not to scale.

Soldier pile and lagging

Steel H-piles are driven or drilled in at regular intervals before digging starts, often at about 6 to 8 ft centers. As the excavation goes down, crews fit lagging of timber, steel plate or precast concrete between the piles. It is quick, adjustable on site and usually one of the cheaper options, which is why it is the default for many temporary cuts.

The weakness is water. Shore Systems notes that it cannot be used in high water table conditions without extensive dewatering. It is also less stiff than the continuous walls, and poor backfilling behind the lagging can lead to ground loss and surface settlement. Near a sensitive building, that matters more than the price. Caltrans also classes these walls by support: cantilevered if they stand on embedment alone, or anchored when ground anchors are added.

Continuous flight auger drilling into sandy soil beside a yellow rig
Auger drilling on a site. Soldier piles are often set in drilled holes where driving is not suitable. Photo: Pexels.

Steel sheet pile walls

Interlocking steel sheets are driven, vibrated or pressed in along the line of the excavation, forming a continuous barrier before any soil comes out. They are especially useful when the dig goes below groundwater, and the same sheets form cofferdams and bulkheads. Sheet piles are generally less expensive than the drilled options and can often be pulled and reused on temporary work.

Boulders and large obstructions are the main problem, because sheets can deflect or tear rather than get through them. Driving and vibrating can also be a concern close to existing structures, so ask about hydraulic pressing where that applies.

Aerial view of steel sheet piles enclosing a foundation pit, an excavator beside it and spare sheets stacked on the ground
Steel sheet piles enclosing a foundation pit, with spare sections stacked at lower right. Photo: Pexels.

Secant and tangent pile walls

Both are rows of drilled concrete piles. In a secant wall the piles overlap, cutting into each other to make a continuous, water-resistant wall. Drilling can get through fill, cobbles and even old concrete, and the wall is stiff, which helps protect neighboring buildings. The downside is cost, and the need for an experienced shoring contractor.

In a tangent wall the piles sit side by side without overlapping. You lose the watertightness, but the wall is easier to build and very robust, which makes it useful where tiebacks are not possible because of site logistics or easement limits.

Teal crawler-mounted piling rig on a sandy construction site
A crawler piling rig of the kind used for drilled pile walls. Photo: Pexels.

Soil nail walls

A soil nail wall is built from the top down. The excavation advances in lifts, commonly 3 to 5 ft high, and at each lift crews drill and grout steel nails into the ground and spray an initial shotcrete facing. The FHWA manual says nails are most often placed at 4 to 6 ft spacing vertically and horizontally. A final shotcrete or cast-in-place facing follows. Nearly all the equipment is compact, so soil nailing works well on tight sites.

It only works if the ground will stand unsupported for a short time. FHWA GEC 7 lists these as generally unsuitable or more difficult and expensive for soil nailing:

  • Dry, poorly graded cohesionless soils
  • Granular soils with high groundwater
  • Soils with many cobbles and boulders
  • Soft to very soft fine-grained soils, with SPT N-values under 4
  • Collapsible soils
  • Organic soils such as peat

Slurry and diaphragm walls

A trench is excavated in panels under a stabilizing slurry, then filled with reinforced concrete to form a thick, continuous wall. These walls are stiffer than sheet piling and hold soil better than soldier piles and lagging. They are often used for deep, demanding excavations. Caltrans notes that where overhead room is limited, concrete diaphragm walls can be used with ground anchors. Expect this to be the most expensive option on this list.

Tiebacks and internal bracing

These are not walls. They are how a wall gets extra support as it gets deeper. Tiebacks, or ground anchors, are stressed from the wall face into stable ground behind it. They keep the pit clear of struts, but they extend under the neighboring land, so you need that owner’s permission and clear utility records. Internal bracing and rakers stay inside the excavation. They avoid the easement problem, but they obstruct the work and have to be sequenced around construction.

Shortlist a system for your site

Earth retention selector

A first shortlist based on the guidance in this article. It is not a design.

How to choose: the factors engineers check

Caltrans lists the main factors for selecting an earth retaining system. Grouped into practical questions, they are:

  • Ground: soil types, settlement limits, liquefaction potential and corrosiveness.
  • Water: where groundwater sits and whether dewatering would disturb nearby structures.
  • Neighbors: foundations, utilities and how much movement they can tolerate.
  • Space: equipment access, traffic staging, right-of-way and easements.
  • Sequence: top-down or bottom-up construction.
  • Life: temporary or permanent service, maintenance and appearance.
  • Cost and time for design and construction.

Note that conventional retaining walls and MSE walls are usually built from the bottom up and backfilled, so they suit fill situations rather than a cut next to something you cannot disturb. The soil loads on any of these walls come from the same theory, covered in our Rankine earth pressure guide with worked examples.

What earth retention costs

There is no reliable public price list, so treat any figure as a starting point. Two reference points are useful:

SystemReported cost per sq ft of wallSource and date
Anchored steel sheet pile$47.69NASSPA study, 2009
Soldier pile and concrete lagging$90.45NASSPA study, 2009
MSE wall$95.58NASSPA study, 2009
Slurry wall$210.60NASSPA study, 2009
Soil nail wall$30 to $80Contractor estimate, undated
Anchored soldier pile$50 to $100+Contractor estimate, undated

Read these with care. The NASSPA figures describe one hypothetical 100-ft wall, are many years old, and come from a sheet pile trade association, which has an obvious interest in the result. Use them for rough ranking, not budgeting. As an illustration, a 12-ft cut along 100 ft is 1,200 sq ft of wall face. At those 2009 rates that spans roughly $57,000 for sheet pile to $253,000 for a slurry wall. Current prices will be higher, and depth, soil, water and access can change the order entirely.

Dewatering, monitoring, tiebacks and permits are often priced separately, so compare bids line by line. The cost of the wall also has to be weighed against damage to a neighbor. See how to judge settlement cracks for what that movement can look like. For smaller garden and site walls, our retaining wall cost guide is a better fit.

How we checked this guide

OSHA thresholds are from the regulation text. Soil nail lift heights, spacing and unsuitable soils are from FHWA GEC 7. System definitions and selection factors are from the Caltrans Bridge Design Practice, Chapter 11.2 (2022). Practical strengths and limits come from contractor guidance, which we label as such. The selector is our own simplified scoring built from those sources. Cost figures are reported values we could not independently confirm, so we show their origin and age. This article is general information. A licensed geotechnical or structural engineer must design any retention system.

Sources: OSHA 1926.652; OSHA Subpart P Appendix B; FHWA GEC 7, Soil Nail Walls; Caltrans Bridge Design Practice 11.2; Shore Systems, excavation support; North American Steel Sheet Piling Association, Retaining Wall Comparison Technical Report, 2009. Last reviewed November 2026.

Frequently asked questions

What is an earth retention system?
It is a structure that holds back soil so an excavation can stay open safely, or so a grade change can be permanent. Common types are soldier pile and lagging, sheet piles, secant piles, soil nail walls and slurry walls.
What is the difference between shoring and earth retention?
The terms overlap. Shoring usually means temporary support during excavation, while earth retention also covers permanent walls. A soil nail wall, for example, can be either.
Which earth retention system works below the water table?
Sheet piles, secant piles and slurry walls are the usual choices. Soldier piles need extensive dewatering in high groundwater, and soil nails are difficult in granular soils with high groundwater.
What is the cheapest earth retention system?
It depends on the site, but soldier pile and lagging, sheet piles and soil nail walls are generally the lower-cost options where the ground suits them. Secant and slurry walls usually cost more.
When does an excavation need an engineer?
OSHA requires sloping or benching over 20 ft deep to be designed by a registered professional engineer, and support systems that do not use OSHA’s appendices or tabulated data must be approved by one. In practice, most systems beside a structure or road are engineered regardless of depth.
Are soil nail walls permanent?
They can be. FHWA says they are permanent structures in most US roadway projects, though they are also built as temporary shoring lasting a few months.
Stop calculating by hand — go Pro

Unlock an ad-free experience plus a growing library of ready-to-use civil-engineering calculators, IS-code cheat-sheets and formula PDFs. From just ₹99.

Go Pro →

Discover more from The Civil Studies

Subscribe to get the latest posts sent to your email.

Fuel Free Learning Support TheCivilStudies

Keep civil engineering knowledge free — articles, calculators, and practical site guides for everyone.

Choose an amount

100% Secure · Powered by Cashfree

TheCivilStudies Team
TheCivilStudies Team

TheCivilStudies is an independent civil-engineering learning site from India. Our guides explain IS-code provisions, formulas, worked examples and site practice for students and working site engineers. Calculations are checked against the relevant Indian Standard, and articles are updated when codes or practice change. Spotted an error? Tell us in the comments and we will fix it.