How India’s Bullet Train Is Being Built: Full Span Girders, J-Slab Track and the Undersea Tunnel

How the Mumbai–Ahmedabad bullet train is built: 970 tonne full span girders, J-slab ballastless track, the 21 km tunnel under Thane Creek, and dated 2026 progress figures.

India’s first bullet train is no longer a drawing. By September 2026, the Railway Minister reported 371 km of viaduct and 456 km of piers on the 508 km Mumbai–Ahmedabad corridor. Most news stories stop at the numbers. This guide explains how the corridor is actually being built: why almost all of it is elevated, how a 970 tonne girder is placed in one lift, what “J-slab” track is, and how the 21 km tunnel under Mumbai and Thane Creek is being dug. Every figure is dated, because they change every month.

Mumbai–Ahmedabad bullet train: quick answer
The corridor is 508 km long with 12 stations, and about 465 km of it is elevated. Most of the viaduct is built with the full span launching method: a whole 40 m prestressed concrete box girder of about 970 tonnes is cast in a yard and lifted onto the piers in one operation. Trains will run on Japanese J-slab ballastless track, with a maximum speed of 350 km/h and an operating speed of 320 km/h. The government targets the first section, Surat–Vapi, in 2027.
ItemFigureAs of
Piers452 km / 456 km22 Jul 2026 / Sep 2026
Girders / viaduct356 km girder work / 371 km viaduct22 Jul 2026 / Sep 2026
Track bed209 km22 Jul 2026
OHE masts9,300+ of about 22,000Sep 2026
Tunnel (Maharashtra)about 5 km of 21 kmSep 2026

The corridor in one paragraph

The Mumbai–Ahmedabad High Speed Rail (MAHSR) is built by the National High Speed Rail Corporation Limited (NHSRCL) using Japanese Shinkansen technology. It runs 508 km from an underground terminal at Bandra Kurla Complex (BKC) in Mumbai to Sabarmati in Ahmedabad, with 12 stations. The Railway Minister has said the maximum speed will be 350 km/h with trains operating at 320 km/h, and the full journey is expected to take about 1 hour 58 minutes. Of the 12 stations, BKC is underground and the other 11 are elevated.

Why the line is almost all viaduct

About 465 km of the 508 km is on viaduct. An elevated line looks expensive, but on this route it solves several problems at once:

Civil Site Engineer Bundle — Concrete QC Handbook + RCC Lap Length Excel cover
📚 Recommended Download
Civil Site Engineer Bundle — Concrete QC Handbook + RCC Lap Length Excel
Our two best-sellers in one download: the 238-page Concrete Site Handbook kit plus the IS 456 lap-length Excel toolkit and quick-reference PDF.
✔ IS 456 based  ·  ✔ Instant download  ·  ✔ Lifetime access
₹1098₹299
Get the Bundle →
  • Land: a viaduct needs a narrow strip for pier foundations, not a wide embankment. On a densely farmed and built-up coastal belt, that matters.
  • No level crossings: a 320 km/h train cannot share the ground with roads, cattle and people. Going over everything removes the conflict.
  • Soft soil and flooding: much of the route crosses soft coastal ground and seasonal rivers. Deep pile foundations and a raised deck avoid the long-term settlement and flood risk of a high embankment, and settlement is the enemy of a track that must stay within millimetres.
  • Repetition: hundreds of kilometres of identical 40 m spans can be made like a factory product. That is what makes the full span method possible.

Full span launching: a 970 tonne girder in one lift

Most metro viaducts in India are built segment by segment: short precast pieces are hung from a launching girder and stressed together. MAHSR uses that too in some places, but the bulk of the viaduct uses full span launching. Each span is a single 40 m prestressed concrete (PSC) box girder, cast in one piece in a casting yard near the alignment. NHSRCL figures put each girder at about 390 m³ of concrete and 42 tonnes of steel, for a weight of roughly 970 tonnes.

Diagram of the full span launching method: girder cast in yard, lifted by straddle carrier, carried along the finished deck by a girder transporter and placed by a launching gantry
The four steps of full span launching. Simplified, not to scale.

The sequence works like this:

  1. Cast and cure in the yard. The full girder is cast in a reusable steel mould, cured and prestressed under controlled conditions. Quality is far easier to control in a yard than on top of a pier.
  2. Lift and stack. A straddle carrier, a heavy gantry crane running on rails in the yard, lifts the finished girder and moves it to storage or to the loading point.
  3. Transport along the finished deck. A girder transporter, a multi-axle vehicle, carries the girder along the spans that are already in place to the working face.
  4. Launch. A full span launching gantry standing on the piers takes the girder from the transporter, moves it forward and lowers it onto its bearings. The gantry then moves itself forward to the next span. The first few spans out of each yard are placed with a pair of bridge gantries before the transporter can run on the deck.

The Railway Minister has called the method about ten times faster than conventional segmental construction, and the cranes that lift more than 1,000 tonnes are designed in India. The trade-off is that the method needs very large casting yards, very heavy equipment, and a run of standard spans. Where the line crosses rivers, highways and railways, or needs longer spans, other methods take over.

Precast concrete box girder viaduct deck on a pier, with scaffolding below, during elevated railway construction
A precast box girder viaduct being built for an elevated railway in the Philippines, shown for illustration. Photo: FBenjr123, CC BY-SA 4.0, via Wikimedia Commons.

Where full span does not fit

  • Segmental spans: precast segments joined on site are used where spans are not standard or access for full span equipment is difficult.
  • Steel bridges: over existing railway lines and highways, steel truss bridges are assembled and pushed into place so traffic below can keep running. NHSRCL launched its first steel bridge in Maharashtra in September 2026.
  • River bridges: large rivers such as the Narmada, Mahi and Sabarmati need well or pile foundations in the riverbed and longer spans. The Sabarmati bridge was built by the balanced cantilever method, which we explain in our Sabarmati river bridge article. In July 2026 the Ministry reported 21 of 25 well foundations on the Narmada bridge and 11 of 12 on the Mahi bridge.

J-slab track: why there is no ballast

Ordinary Indian Railways track sits on crushed stone ballast, which needs regular tamping to keep its shape. At 320 km/h, the track geometry has to stay almost perfect, and ballast can also be thrown up by fast trains. MAHSR therefore uses Japan’s J-slab ballastless track, with the concrete slabs made in Indian casting yards.

In the Japanese slab track system, the layers from bottom to top are typically:

  • Reinforced concrete track bed, cast on the viaduct deck.
  • Cement asphalt mortar (CAM) layer, injected under each slab. It fills the gap, adjusts the final level and adds some resilience.
  • Precast track slabs, positioned by stoppers so they cannot slide along or across the track.
  • Fastenings and rails on top, with the fastenings allowing small final adjustments.
Diagram of slab track layers: rails and fastenings, precast track slab, cement asphalt mortar layer, RC track bed and viaduct deck, with a stopper
Typical layers of Japanese slab track, simplified. Not to scale.

The benefit is low maintenance and stable geometry for decades. The cost is that the structure underneath must not settle, because you cannot simply tamp a concrete slab back into line. That is one more reason for the deep foundations and the elevated alignment. As of 22 July 2026, the Ministry reported 209 km of track bed laid, and about 87% of the track bed on the Surat–Vapi stretch.

The 21 km tunnel and the undersea section

In Maharashtra, the line leaves BKC in a 21 km tunnel, of which about 7 km runs beneath Thane Creek. Two tunnelling methods are used:

  • Tunnel boring machines (TBMs) for the long bored sections, including under the creek. Two TBMs were launched in July 2026 from Vikhroli and Sawli. Each weighs more than 3,000 tonnes, is 96 m long and has a 13.6 m diameter cutterhead.
  • Mountain tunnelling, also known as the New Austrian Tunnelling Method (NATM), on a section between Ghansoli and Shilphata. NATM excavates in stages and supports the rock with shotcrete, rock bolts and steel ribs, letting the ground carry part of its own load. About 5 km had been excavated this way by September 2026.

The BKC station itself is about 32 m deep, with three levels and six platforms, each more than 400 m long. For more on the undersea section and tunnel linings, read our articles on India’s first undersea bullet train tunnel and concrete lining in tunnels.

Power and systems

The line uses a 2×25 kV compound catenary for traction power. About 22,000 steel overhead equipment (OHE) masts are needed, and more than 9,300 had been installed by September 2026. In late October 2026 NHSRCL also briefed the media on the corridor’s 14 traction substations. Signalling, rolling stock supply and testing still have to follow the civil work, and that is where most schedule risk now sits.

Green and white Shinkansen E5 series train at a platform in Tokyo Station
A Shinkansen E5 series train at Tokyo Station. MAHSR is built with Shinkansen technology. Photo: Pranorup, CC BY-SA 4.0, via Wikimedia Commons.

When will it open?

Official statements point to the first section, about 100 km between Surat and Vapi, opening in 2027. A Business Today report from August 2026 gave the target as August 2027. A piece written by the Railway Minister and published in October 2026 said the first service is scheduled to begin in the final quarter of 2027. The full corridor has been talked about for the end of 2029, but the Ministry says the date depends on civil, track, electrical, signalling and train supply work all coming together. Treat any single date with caution until the trains are on test.

What civil engineers can learn from MAHSR

  • Industrialise the repetitive part. Full span launching turns a viaduct into a production line. The same idea applies to any project with many identical elements.
  • Design for settlement, not just strength. Ballastless track forgives almost nothing, so foundation design is driven by long-term movement.
  • Use the right method for each zone. One corridor uses full span, segmental, balanced cantilever, steel truss, TBM and NATM. Good engineering is choosing well between them.
  • Logistics is engineering. Moving a 970 tonne girder safely along a finished deck is as much a design problem as the girder itself.

If you like large Indian rail projects, our explainers on the Chenab rail bridge and the Mumbai–Pune Missing Link tunnels cover two more.

How we checked these numbers

Progress figures come from two dated sources that measure slightly different things: a Ministry of Railways update of 22 July 2026 reported by Business Today, and figures “as of September 2026” in a piece by the Railway Minister published by Metro Rail Today. We show both instead of mixing them. Girder weight, concrete and steel quantities come from NHSRCL statements reported in the trade press. The description of J-slab layers is the standard Japanese slab track arrangement; NHSRCL has not published slab dimensions, so we give none. NHSRCL’s own progress page was not reachable when we checked, so confirm the latest numbers on nhsrcl.in. Last reviewed November 2026.

Sources: NHSRCL; Business Today, August 2026; Metro Rail Today, October 2026; Metro Rail News, first 40 m full span girder; PSU Connect, full span launching method; Swarajya, viaduct progress.

Frequently asked questions

How long is the Mumbai–Ahmedabad bullet train route?
The corridor is 508 km long with 12 stations. About 465 km is elevated, the Mumbai terminal at BKC is underground, and there is a 21 km tunnel in Maharashtra, including about 7 km under Thane Creek.
What is the full span launching method?
It is a viaduct construction method in which a complete span, here a 40 m prestressed concrete box girder of about 970 tonnes, is cast in a yard, carried along the finished deck by a girder transporter and placed on the piers in one lift by a launching gantry. It is much faster than building the span from small segments.
What is J-slab track?
J-slab is the Japanese ballastless slab track system. Precast concrete track slabs sit on a cement asphalt mortar layer over a reinforced concrete track bed, held in place by stoppers, with the rails fastened on top. It keeps track geometry stable with little maintenance.
When will India’s first bullet train start?
The government targets the first section, Surat to Vapi, in 2027. One August 2026 report said August 2027, while an October 2026 piece by the Railway Minister said the final quarter of 2027. The full corridor depends on civil, track, electrical, signalling and train supply work.
How fast will the bullet train run?
The Railway Minister has said the maximum speed will be 350 km/h with an operating speed of 320 km/h, and a Mumbai to Ahmedabad journey of about 1 hour 58 minutes.
How much of the bullet train project is complete?
As of 22 July 2026, the Ministry reported 452 km of piers, 356 km of girder work and 209 km of track bed. Figures given for September 2026 were 456 km of piers and 371 km of viaduct. Check NHSRCL for the latest update.
Stop calculating by hand — go Pro

Unlock an ad-free experience plus a growing library of ready-to-use civil-engineering calculators, IS-code cheat-sheets and formula PDFs. From just ₹99.

Go Pro →
Fuel Free Learning Support TheCivilStudies

Keep civil engineering knowledge free — articles, calculators, and practical site guides for everyone.

Choose an amount

100% Secure · Powered by Cashfree

TheCivilStudies Team
TheCivilStudies Team

TheCivilStudies is an independent civil-engineering learning site from India. Our guides explain IS-code provisions, formulas, worked examples and site practice for students and working site engineers. Calculations are checked against the relevant Indian Standard, and articles are updated when codes or practice change. Spotted an error? Tell us in the comments and we will fix it.

Articles: 449