How Many Bags of Concrete per Fence Post? Chart + Calculator

Bags of concrete per fence post for 4×4, 6×6 and chain link posts, the hole size to dig, and a free calculator.

Setting fence posts? Here is how many bags of concrete each post needs, for 4×4 and 6×6 wood posts and round chain-link posts, plus the hole size to dig and a free calculator in inches.

Bags of concrete per fence post: quick answer
A 4×4 post in a 10 in × 30 in hole (24 in of concrete over 6 in of gravel) needs about 0.92 ft³: that is 2 bags of 80 lb concrete or 3 bags of 50 lb fast-setting mix. A 6×6 post in a 16 in × 36 in hole needs about 5 bags of 80 lb.
4×4 post, 6 ft fence2 × 80 lb or 3 × 50 lb fast-setting
6×6 post, 8 ft fence5–8 × 80 lb (hole size matters)
Chain link line post (2⅜ in)2 × 50 lb fast-setting
Hole diameterAbout 3× the post width
Hole depthAbout ⅓ of fence height, plus 6 in gravel
Rules of thumb used by US fence installers and bag manufacturers. Local code and frost depth can require deeper holes.
Fence Post Concrete Calculator

How big should a fence post hole be?

  • Diameter: about 3 times the width of the post. A 4×4 (actual 3½ in) needs a 10–12 in hole; a 6×6 (actual 5½ in) needs 16–18 in.
  • Depth: about one-third of the post height above ground, and at least 24 in. A 6 ft fence needs about 24 in of post in the ground; an 8 ft fence about 32 in.
  • Gravel: add about 6 in of gravel at the bottom so water drains away from the end grain of wood posts.
  • Frost line: in cold climates, take the hole below the local frost depth so frost heave does not lift the post. Your building department can tell you the depth.
  • Gates and corners carry more load. Use the larger hole size there.

Concrete per fence post chart

PostHole (diameter × depth)Concrete per post50 lb fast-setting bags80 lb bags
4×4 wood (3.5 in)10 in × 30 in0.92 ft³32
4×4 wood (3.5 in)12 in × 30 in1.40 ft³43
4×4 wood (3.5 in)10 in × 36 in1.15 ft³42
6×6 wood (5.5 in)16 in × 36 in2.97 ft³85
6×6 wood (5.5 in)18 in × 42 in4.67 ft³138
2⅜ in steel (chain link line post)8 in × 30 in0.64 ft³22
2⅜ in steel (chain link line post)10 in × 36 in1.29 ft³43
Assumes 6 in of gravel at the bottom and concrete filled to ground level around the post. Bags rounded up per post.

How the calculation works

  1. Concrete height = hole depth − gravel depth
  2. Hole volume = 3.1416 × (diameter ÷ 2)² × concrete height (cubic inches)
  3. Subtract the post: post width × post thickness × concrete height (or 3.1416 × radius² for a round post)
  4. Divide by 1,728 to get cubic feet
  5. Divide by the bag yield (0.60 ft³ for 80 lb, 0.45 ft³ for 60 lb, 0.375 ft³ for 50 lb fast-setting) and round up

Worked example: 20 posts for a 6 ft privacy fence

  1. Post: 4×4 (3½ in) for a 6 ft fence. Guideline hole: 10 in wide × 30 in deep (24 in of post in the ground plus 6 in of gravel)
  2. Concrete height = 30 − 6 = 24 in
  3. Hole = 3.1416 × 5² × 24 = 1,885 in³; post = 3.5 × 3.5 × 24 = 294 in³
  4. Concrete = (1,885 − 294) ÷ 1,728 = 0.92 ft³ per post
  5. 80 lb bags: 0.92 ÷ 0.60 = 1.53, so 2 bags per post, 40 bags for 20 posts
  6. Or 50 lb fast-setting: 3 bags per post, 60 for 20 posts
  7. Gravel: about 5.5 ft³ for all 20 holes

Fast-setting or regular concrete for posts?

Fast-setting (50 lb)Regular mix (60/80 lb)
How you use itPour dry into the hole, then add waterMix in a tub or wheelbarrow first
Sets inAbout 20–40 minutesSeveral hours
Concrete per bagLess (≈0.375 ft³)More (0.45–0.60 ft³)
Best forFence posts, mailboxes, quick jobsGate posts, many holes, lower cost per ft³
Follow the set and cure times on the bag. Wait before hanging gates or attaching heavy panels.

How to set a fence post in concrete

  1. Call 811 before you dig so buried utility lines are marked.
  2. Dig the hole to full depth, slightly wider at the bottom than the top.
  3. Add about 6 in of gravel and tamp it.
  4. Set the post, then brace it plumb in two directions.
  5. Fill with concrete to just below ground, then slope (crown) the top away from the post so water runs off.
  6. Let it cure as the bag directs before attaching rails or gates.

FAQ

How many bags of concrete do I need per fence post?

For a 4×4 post in a 10 in × 30 in hole with 6 in of gravel, about 2 bags of 80 lb concrete or 3 bags of 50 lb fast-setting mix. A 6×6 post needs about 5 bags of 80 lb in a 16 in × 36 in hole.

Building Estimate & BOQ Excel Kit cover
📚 Recommended Download
Building Estimate & BOQ Excel Kit
Type your building dimensions — get quantities, materials, a priced BOQ and cost per sq ft. 6 linked sheets, IS 1200-style measurement, editable rates.
✔ Editable Excel  ·  ✔ Instant download  ·  ✔ Lifetime access

How deep should a fence post be?

About one-third of the height above ground, and at least 24 in, plus about 6 in of gravel. Go below the frost line in cold climates.

How wide should a fence post hole be?

About 3 times the post width: 10–12 in for a 4×4 and 16–18 in for a 6×6.

Can I use fast-setting concrete for fence posts?

Yes. Pour it dry into the hole and add water as the bag directs. It sets in roughly 20–40 minutes but each bag fills less volume than regular concrete.

How many 50 lb bags of fast-setting concrete per post?

About 3 for a 4×4 post in a 10 in × 30 in hole, and about 8 for a 6×6 post in a 16 in × 36 in hole.

Hole sizes are common US installer guidelines; bag yields are typical values printed on US bagged concrete. Local codes, frost depth and wind loads can require larger or deeper holes.

Stop calculating by hand — go Pro

Unlock an ad-free experience plus a growing library of ready-to-use civil-engineering calculators, IS-code cheat-sheets and formula PDFs. From just ₹99.

Go Pro →

Discover more from The Civil Studies

Subscribe to get the latest posts sent to your email.

Fuel Free Learning Support TheCivilStudies

Keep civil engineering knowledge free — articles, calculators, and practical site guides for everyone.

Choose an amount

100% Secure · Powered by Cashfree

TheCivilStudies Team
TheCivilStudies Team

TheCivilStudies is an independent civil-engineering learning site from India. Our guides explain IS-code provisions, formulas, worked examples and site practice for students and working site engineers. Calculations are checked against the relevant Indian Standard, and articles are updated when codes or practice change. Spotted an error? Tell us in the comments and we will fix it.

Articles: 442